# How Project Progress Is Calculated in NIZU > In NIZU, the project progress bar provides a visual representation of how far a project has advanced not just by the number of tasks completed, but by the value and complexity of those tasks. This en… - Page: https://dashboard.nizu.io/knowledge_base/view/46-how-project-progress-is-calculated-in-nizu - Part of: [Knowledge base](https://dashboard.nizu.io/knowledge_base/llms.txt) on NIZU — https://dashboard.nizu.io/llms.txt - Updated: 2026-10-25T11:50:03Z In **NIZU**, the **project progress bar** provides a visual representation of how far a project has advanced not just by the number of tasks completed, but by the **value and complexity** of those tasks. This ensures a more accurate picture of progress, especially when tasks carry different weights. --- #### **How It Works** Each task in a project is assigned a **point value**, reflecting its complexity or importance. - The default point range is **1 to 5**. - You can customize this range in: **Settings > Setup > Task Settings > Task Point Range**. The **progress percentage** is then calculated using the total points from **completed tasks** divided by the **total task points** in the project: > **Project Progress (%) = (Completed Task Points ÷ Total Task Points) × 100** --- #### **Example** Here’s how a project’s progress would be calculated: | **Task** | **Points** | **Status** | | --- | --- | --- | | Task 1 | 1 | ✅ Completed | | Task 2 | 1 | ❌ Not Completed | | Task 3 | 4 | ✅ Completed | | Task 4 | 3 | ❌ Not Completed | | Task 5 | 1 | ❌ Not Completed | - **Total Points:** 1 + 1 + 4 + 3 + 1 = **10** - **Completed Points:** Task 1 (1) + Task 3 (4) = **5** **Progress = (5 ÷ 10) × 100 = 50%** The project progress bar will display **50% completion**. #### #### **Why This Matters** By calculating progress based on **task weight**, teams get a more meaningful insight into real project advancement ensuring efforts are focused where they matter most.